The Central Artery/Tunnel Project included the largest use of slurry walls anywhere
in North America. What's a slurry wall? It was the single most important construction
technique on this gigantic project, the primary tool of the designers to fulfill
the most important promise to the people of Boston: Keeping the city open for
business and traffic moving during more than a decade of construction.
A slurry wall is a concrete wall that runs from the surface of the ground down
to bedrock. It defined the area to be excavated for the underground highway and
eventually formed the actual walls of the new Central Artery. "Slurry" refers
to a clay-water mixture that is pumped into the excavation for the wall to keep
the sides intact until concrete is poured in.
How a slurry wall was constructed:
First, a trench about three feet by ten feet was dug by an excavating machine
down to bedrock, which on the Central Artery project was more than 120 feet down
in some areas.
These images are close-ups of equipment used for slurry wall trenching:
![]() |
![]() |
![]() |
As the earth was removed (either by a clamshell excavator or by a continuous
milling machine that grinds away obstructions with rotating wheels) the liquid
slurry was pumped into the hole.
The clay-water slurry mixture was just heavy enough to keep the walls of these
very deep excavations intact before huge reinforcing steel beams were lowered
into the trenches and concrete pumped in to fill the hole. The concrete displaced
the slurry, which was pumped away and re-used. Each slurry "panel" took about
two days to dig, reinforce, and fill.
The side-by-side panels form the walls of the underground Central Artery. A total
of more than 26,000 linear feet of slurry walls - about five miles worth - went
into the project, one ten-foot trench at a time. Once the walls were in, huge
steel beams were placed between them at ground level and concrete decking placed
on the beams. Traffic and construction equipment moved on the decking as soil
was excavated below and removed through "glory holes" where sections of decking
were removed.
As excavation proceeded, large steel beams called struts were installed between
the walls to counter pressure from the ground and nearby buildings. Once the excavation
reached the proper depth, the reinforced concrete roadbed was laid down, the struts
removed as the roadbed built up, and the excavation filled in to the surface once
the roadway was finished.
Slurry walls were essential to the success of the Central Artery project because
the special excavating equipment can work in confined spaces in a dense old city
such as Boston (the machinery was first developed in Europe), particularly under
the elevated highway where there was no headroom for tall conventional excavators.
The walls produced a rigid work area for excavating the tunnel without the need
for a much wider conventional trench with sloping sides, which would be impossible
in the narrow corridor where the elevated highway stood.
But perhaps the most crucial use of the walls involves the old highway itself.
The existing six-lane elevated highway had to remain in service throughout construction
even as a wider, eight-to-ten-lane expressway was built directly underneath it.
Placement of the decking and excavation of the tunnel required that all of the
footings that supported beams holding up the old road be removed. The entire weight
of the elevated highway shifted onto new supports resting on the slurry walls of the new highway.
So the slurry walls made construction of the new highway possible in the tight
confines of old Boston, and they let the project keep its key commitment to the
city, with surface traffic moving on the decking and the walls holding the crowded
old highway aloft as construction proceeded below.